Construction Update - Q1 2024
As of April 1st, 2024, we're pleased to announce the completion of the first 10 villa-units from Stage 3A. Consequently, we have now initiated Stage 3B, with plans to construct an additional 10 villa-units.
Out of the initial 10 units from Stage 3A, which were introduced to the market on October 23rd. we're delighted to confirm the sale of 8 units. This leaves only 2 units available for sale from this batch, fully completed and ready for occupancy.
For potential buyers, Stage 3B is underway, and 4 of the next 10 villa-units are nearing construction. Notably, 2 units have already been sold, leaving 2 units available for purchase. These remaining units are expected to be finished within the next 30-45 days.
Stage 3B - 2024
Stage 3A - 2023
Construction Update - 2022
The final Villa in Stage 2b (Unit 47) was completed in December 2022.
Stage 2c construction, of 8 new Villa's (units 31 to 39, excluding unit 34), commenced in June 2022 and was completed in late January 2023.
Stage 3 land has now been cleared of undergrowth, forestation and site preparation for construction is currently on foot, with an expected commencement in March 2023.
Stage 3 comprises 3 sections: 3a, 3b, 3c, each consisting of 10 villas, totaling 30 villas overall.
With Stage 2c nearly sold out and 7 deposits already secured for the next 10 units under construction, we suggest securing a new villa.